Board asking for a go-live date before anyone has scoped the work?
A focused first phase — one cloud, one or two processes, minimal integration — typically goes live in 8 to 12 weeks. Sales Cloud with ERP integration runs 10 to 14 weeks, Service Cloud with Field Service 12 to 16, CPQ 12 to 20, and multi-cloud programmes 4 to 9 months across two or three phases.
Indicative ranges from delivered programmes. Your number moves with data quality, integration count and decision speed.
6–8 weeks
Lead-to-opportunity, forecasting, dashboards, user training. Data migration limited to accounts, contacts and open pipeline.
10–14 weeks
Adds account, order and invoice synchronisation with SAP, Oracle, NetSuite or a homegrown ERP, plus reconciliation and error handling.
12–16 weeks
Omni-channel case capture, entitlements and SLAs, knowledge, mobile work orders, scheduling and preventive maintenance.
12–20 weeks
Product and pricing model, configuration rules, approval matrices, document generation, contracts and finance hand-off.
4–9 months in 2–3 phases
Sequenced so the highest-risk revenue process goes live first, with later phases adding clouds, geographies and AI.
4–10 weeks
Depends almost entirely on data readiness and grounding sources rather than on agent configuration.